RED
BLUFF
CITY
COUNCIL
SPECIAL MEETING MINUTES
DATE OF
MEETING:
TIME OF
MEETING:
PLACE OF
MEETING: RED BLUFF
COUNCIL CHAMBERS, CITY HALL
Councilmembers
Present:
Andy Houghton, Mayor
Wayne Brown
Larry
Stevens
Councilmembers
Absent:
Russ Frey
Forrest
Flynn
Staff
Present:
Susan
Price, City Manager
Michael
Damon, Fire Chief
Margaret Van Warmerdam, Finance Director
J. D. Ellison Sr., Building Director/Official
Gary Antone, Public Works Director/City Engineer
Nik Reikalas, Parks & Recreation Director
Donna Gordy, City Treasurer
Lamar Bayles led the Pledge of Allegiance at the request of Mayor
Houghton and the assemblage joined in.
None
MCGLYNN SWIMMING POOL
Nik
Reikalas, Parks & Recreation Director, reviewed the staff report and the
report submitted on the preliminary leak detection which was completed on
1. Main drain concerns
– water epoxy applied immediately to drain cover – Securing the main drain cover
will keep the cover from moving, thus preventing exposure to the main drain and
a suction hazard. This job will be
performed by the Parks and Recreation Department staff and will cost
approximately $10 to repair.
2. The 6” main drain
being sealed in place is of temp design.
It is recommended by the City Building Department that the single drain
be converted to a “T” design per the new pool design mandate of
3. Perimeter leak at
the tile/gutter level – silicone will be applied – This is a major leak area
that was found by American Leak Detection and by applying this silicone
application will address this section.
The Parks and Recreation Department will fill in the necessary grout/tile
area with a cost of approximately $240 and will be performed immediately. A water loss test will be performed by
City staff after the completion of the caulking to determine the actual stopping
of the water leak.
4. Proceed with the
American Leak Detection analysis to determine whether the piping at the returns
and main drain are leaking.
Additional cost of the pipe pressure test will be approximately
$900. The Parks and Recreation
Department would proceed with this test based on the City Council’s
recommendation.
5. A core test should
be completed to ensure no piping has taken place due to the water leakage. This point is stated in the previous
GEOPlus Co. report item #3.
6. The loss of water
should be addressed for the following reasons: conservation of water, added cost
of chemicals, added electrical cost of the well pump supplying the water and
maintenance cost to pump, continuous damage to pool if leaks are not stopped,
possible environmental impact to the ground and the complete added cost to the
City Budget due to the stated reasons.
7. If it is determined
that the pipes are leaking, staff will note how much water and make another
analysis at that time. This repair
is major and would require reconstruction of the return piping as well as the
main drain piping (please see the above item number 2 for repair
reference). The cost to repair the
return line piping as well as address the main drain plumbing and replacement of
the pool deck and gutter system is estimated to be $150,300. Funding for this repair is contained in
the grant that was recently applied for and was anticipated to be fixed within
the next two years utilizing the City’s cash mater ($70,000) and the grant funds
($163,000). It is important to note
that the grant application process is competitive, with more applications
received than funding available, and there is no guarantee that the grant will
be secured. Thus, the City Council
may need to consider other funding options for the needed
repairs.
Susan Price, City Manager, stated that what the City is dealing with
are two main issues and those are:
1. The leakage and how
much and where or how it is occurring.
2. Secondarily the structural analysis that the
Parks and Recreation Director spoke to in terms as to the core
drills.
It has been authorized and continue to proceed with money from a line
item funding the $6,000 structural analysis, but further along during the summer
an additional budget appropriation may need to be made if money is used from
this account for this work.
Mayor Houghton questioned what the total cost would be up to if the
$8,000 was included.
Mr. Reikalas stated that currently $3,100 had been spent and if the
$8,000 was included it would be in excess of
$12,000.
Mayor Houghton requested clarification as to what point these tests
would get the City to.
Ms. Price stated that it would get the City to a point as to
understand exactly what is occurring with the leakage, where and what is
occurring, as well as a structural analysis letting the City know if there are
any structural issues with the pool.
The City has applied several times for grant money from the state, but it
is very competitive. The City
Council may need to look at other funding options for the needed repairs if the
grant is not received.
Mayor Houghton questioned if there was any doubt that repairs would
need to be made underneath.
J. D. Ellison, Building Official/Director, stated that if the leaks
are not stopped it will just make it worse than what it is now.
Ms. Price stated that the City cash match to the grant was $70,000
and in absence of grant funding the City Council could still authorize the
$70,000 to assist with repairs, but you may still need to budget an additional
$35,000. Staff has also spoken with
the City’s insurance and at this time it is unclear as to what will be
covered. A claim will have to be
submitted and the outcome is not clear at this
time.
Mayor Houghton questioned if the pool would have to be closed and
drained to make repairs.
Mr. Reikalas stated that caulking at the gutter level would not
require complete draining, as well as applying the water epoxy to the
drain.
Ms. Price stated that there may be some part of the testing where by
the pool may have to be closed for a day.
Mr. Reikalas stated that if American Leak were to come back and check
the pipes they asked that the pool be closed while doing
so.
Ms. Price stated that what this testing will provide is an analysis
of what needs to be done.
Mayor Houghton questioned that if work is found that needs to be
done, would staff propose that it be held off under the summer season was
over.
Ms. Price stated that she did not know if it’s not an emergency we
could keep it open unless there is a problem with safety.
Mayor Pro Tem Brown questioned if repairs would be done after hours
or close it down.
Mr. Reikalas stated that he would coordinate with the aquatic staff
to make sure that it was done during a time so as to not impact swim lessons or
public swim.
Mayor Pro Tem Brown stated that since at this time the City doesn’t
know if grant money will be received the City actually only has $35,000 to work
with, not the $70,000 as budgeted.
Ms. Price stated that was correct, but that she anticipated that the
Council could fund the other $35,000 if needed. However, staff will bring back to the
City Council some other funding options, which might include some loan
funding. Recommend that staff does
proceed with the tests to obtain the necessary information needed for work that
needs to be done.
Mayor Houghton asked that if anyone from the audience wished to say
anything.
Dave Gunner, resident, questioned if the pool closure would be
permanent or just for repairs and if the pool would be destroyed and rebuilt at
another location.
Ms. Price stated that it was unknown at this time and it is the hope
of everyone to keep that pool operational and that is the purpose of getting
this information.
Mr. Gunner stated that he hoped that it stayed
open.
Mayor Houghton stated that everyone did and that they would not be
spending $12,000 if it was going to be closed.
Mr. Reikalas stated that it was the health and safety aspect that was
the first concern of the City and that the City was looking out for the best
interest of the public.
Daniela
Sartori, concerned citizen, stated that the pool did have a lot of community
support and questioned how the community could help the City Council to obtain
the grants needed for the pool. The
reason this was being asked is because if the pool is closed and with the
Mr. Reikalas stated that a grant official for the grant did visit the
Parks during the last two weeks and that she is aware of the drowning
factor.
Mayor Houghton requested that the City Manager review the future
options for those in attendance so that they know how expensive this may be if
there is major damage.
Ms. Price stated that in the year 2000 the price for renovation was
$1.3 million, however the $1.3 million was broken down to $800,000 for the pool
and another $500,000 for the buildings.
So we may not have to do anything to the buildings at this time. Complete replacement of the pool was
estimated at $2.3 million. The
audience was told that they could contact state legislators about the need for
pool funding.
Robert
Jackson, Tehama County Teacher, expressed his concerns regarding the safety of
the children in
Councilmember Larry Stevens stated that he and Councilmember Russ
Frey attended Legislative Action Day and that packets had been delivered to
Assemblyman LaMalfa, Senator Aanestad and the State Treasurer and that if
letters are written to please make sure that a copy is mailed to the State
Treasurer also. He was told that
there are different funding sources and if they find that the community is
behind what the City is trying to do, it’s very important.
Ms.
Price stated that if calls are made or letters were written to be sure to note
in it that it was understood that the City of
M/S/C Brown, Stevens to prepare letters for the Mayor’s signature to
the State Legislators requesting Legislative Appropriation and to approve the
expenditure of up to $8,000 from Fund 60-62-Special Supplies and Services for
the continued work of the consultant.
AYES: Councilmembers:
Brown, Houghton and Stevens
NOES:
None
ABSENT OR NOT VOTING: Councilmembers: Flynn and Frey (both
absent)
At
s/b Andy
Houghton
Mayor
ATTEST: